Solid Engineering, a trusted and professional engineering firm, has been engaged by our long-term client, BIS, to undertake a track frame rebuild for one of their Mules in their hire fleet. BIS, a prominent player in the underground coal mining industry, maintains a large fleet of hire equipment used in coal mines, with Mules being heavy-lift, track machines powered by electricity. These machines are crucial for moving Longwall roof supports during Longwall relocations.

Solid Engineering has been responsible for the comprehensive maintenance of BIS’ Mule fleet, including servicing, repairs, pre- and post-hire inspections. In addition to these routine tasks, we were entrusted with the track frame rebuild project. The scope of our work encompassed the following activities:

1. Disassembly: We meticulously stripped down the entire track frames on both sides of the Mule.

2. Drafting:
Accurate drafting was performed to ensure precise measurements and compatibility with existing components.

3. Section Replacement:
Worn sections were expertly cut off, and new sections were fabricated and welded in their place.

4. Machining:
As required, various items were machined to ensure proper fit and functionality.

5. Protective Coatings:
We applied high-quality protective coatings to enhance durability and prevent corrosion.

6. Reassembly:
All new or overhauled components were carefully reassembled to restore the track frame’s integrity.

7. Factory Acceptance Testing and Commissioning:
Thorough testing and commissioning procedures were conducted to ensure the rebuilt track frame met the required specifications and safety standards.

8. Project Documentation:
Detailed documentation was prepared, including progress reports, quality control records, and as-built drawings.

Solid Engineering collaborated with trusted and long-term subcontractors to successfully execute certain aspects of the project. Their expertise and support contributed to the seamless completion of the track frame rebuild.

Solid Engineering has successfully completed the track frame rebuild for the first Mule in BIS’s hire fleet. The rebuilt track frame now exhibits enhanced structural integrity and reliability, contributing to the efficient movement of Longwall roof supports during relocations. Our commitment to quality workmanship, customer satisfaction, and adherence to project timelines has been instrumental in delivering outstanding results.

Based on our exceptional performance, BIS has entrusted Solid Engineering with a second Mule track frame rebuild, further solidifying our long-standing partnership and reinforcing our reputation as a dependable engineering firm.

At Solid Engineering, we continue to uphold our motto, “when quality counts,” by delivering superior customer service and the highest quality products to our clients in the mining, infrastructure, construction, manufacturing, and agricultural sectors.